Completed Projects
Computerization of Police Stations District Swat
Online Litigation Management and Case Tracking System for Services Tribunal
Virtual Teacher/Computer based teaching and learning CDs
Web Hosting/Web Portal for Govt. of NWFP
IT Training for IT professionals
Establishment Of One Computer Lab in Schools/Colleges In NWFP
Computerization of Police Stations District Swat
Name of Project
Computerization of Police Stations District Swat
Date of approval
Actual:     10th September 2004
Revised:  15th December 2006
Total Cost
Actual:        Rs. 18.216 Million
Revised:     Rs. 25.175 Million 
Completion Date
Actual:  September 2007
Revised
Achievements
  1. Data Entry  have been started at all Police Stations in District Swat.Total of entered FIR 3204.
  2. Total of Old FIR collected on Forms 8496.
  3. Website for Frontier Police www.frontierpolice.gon.pk
  4. Mobile snatching, Vehicle verification, Complaint system, information to police.
Current Status
Software has been implemented and source code handed over to the Project. Hardware is in place. Posts have been created through current budget. The posts are being filled.
Online  Litigation  Management & Case Tracking System for Service Tribunal
Name of Project
Online  Litigation  Management & Case Tracking System for Service Tribunal
Date of approval
Actual:     10th September, 2004
Revised:  25th  April  2007
Total Cost
Actual:        Rs. 6.345  Million
Revised:     Rs. 5.380  Million 
Completion Date
Actual:      September,  2006
Revised:   June,  2007
Achievements
  1. Software has been commissioned, data entry completed and being updated live in all the 3 courts for the 1250 under trial cases. Posts have been created for the project through current budget and recruitment is in progress. The system is being handed over to the Tribunal. Technical support is being provided by the DoIT as a stop gap arrangement till the arrival of the Tribunals own technical staff.
  2. Website http://www.servicetribunal.gon.pk is operational & integrated with database.
  3. Data Entry of 12,000 Decided & Current Cases is Outsourced.
  4. Approx. 6000 Cases/Files are entered in database via OLM&CTS Software.
Current Status
System has been implemented successfully
Virtual Teacher/Computer based teaching and learning CDs for Schools in NWFP
Name of Project
Virtual Teacher/Computer based teaching and learning CDs for Schools in NWFP
Date of approval
Actual:     5th October, 2005
Revised:  13th November 2007
Total Cost
Actual:        Rs. 22.84  Million
Revised:     Rs. 26.548 Million 
Completion Date
Actual:     October, 2007
Revised:  June, 2008
Achievements
  1. Virtual CDs for the courses of 9th & 10th  Class (Physics, Maths, Chemistry) have been developed.
  2. The infrastructure two schools from each districts has been established.
    One Computer and one Multimedia along with furniture has been provided to 48 Schools.
  3. Virtual Teaching Labs are functional in all the districts
  4. The contents of CDs are being refined and updated and latest versions provided to the Schools.
Current Status
The project is implemented in schools successfully
Web Hosting/Web Portal for Govt of NWFP
Name of Project
Web Hosting/Web Portal for Govt of NWFP
Date of approval
Actual:  September 2004
Total Cost
Actual:        Rs. 13.5000 Million
Completion Date
Actual:        June 2008
Achievements
The e-mail addresses for the officers/officials have been created and tested accordingly and the same have been forwarded to ST&IT Department for onward dissemination to the concerned departments.A website has been launched and is being updated regularly.

The email addresses for Government officials of Governor Secretariat, Governor House, Chief Minister’s Secretariat, Chief Minister’s House, Ministers, MPA’s and Civil Secretariat had been created. Training of all Government Departments (Secretariat Level) and Private Secretaries to the Provincial Ministers on Email addresses had been completed.

Establishment Of One Computer Lab in Schools/Colleges In NWFP
Name of Project
Establishment Of One Computer Lab in Schools/Colleges In NWFP
Date of approval
Actual:     April  2005
Total Cost
Actual:        Rs. 29.206  Million 
Completion Date
Actual:      June, 2008
Achievements
  1. Twenty (20) computer labs have been established in 20 secondary/higher secondary schools in NWFP
  2. During the current financial year 2007-08 twenty (20) computer labs will be established in the remaining secondary/higher secondary Schools (Female) in NWFP.
  3. 20 Male IT Teachers have been recruited
  4. 20 Female IT Teachers will be recruited
Current Status
20 computer labs in 20 female schools are established